Roof and floor slab concreting is a major construction
activity in a building, whether it is an individual house or a
flat. Often errors occur because the operations involved in slab
concreting are not organised properly. Important steps that help
in proper execution are listed below:
Formwork and scaffolding:
The formwork should be strong and the struts erected braced in
both directions. All joints in formwork should be properly sealed.
It is not proper to use mud, jute or paper to seal the openings
in the formwork. Proper putty with grease and cement will seal
the joint perfectly. Strips of steel sheet may be used to seal
large size openings.
Preparation of grill:
The reinforcement grill should be made ready as per the designer's
requirement and checked by him before concreting. The reinforcements
have to be supported by the cover blocks of proper size and quality.
The density and impermeability of the cover block should match
the surrounding concrete. Poor mortar cover blocks should not
be used as they get crushed under the weight of the grill. The
rebars in the top layer is likely to be bent down during the concreting
operation. Therefore, they should be provided with `chairs' made
up of steel and supported at the correct level above the centring
sheet.
Inserts in slab:
A number of functional inserts, such as electrical conduits, M.S.
boxes and fan hooks are embedded in the slab. The location and
positioning of these should be based on electrical wiring diagram
or light and fan points. The inserts should be positioned near
the mid depth of the slab so that they do not reduce the flexural
rigidity of the slab. Positioning them very near the surface should
be avoided.
Collection of material:
In case of site-mixed concrete, adequate quantity of cement, sand,
water and metal required for casting should be collected at site.
In case of ready mixed concrete, the time of arrival, machinery
required for pumping and adequacy of formwork should be ensured.
Construction joints:
The work has to stop at the construction joint. The joint location
and the type of treatment to be given at the joints should be
pre-planned. It may be necessary to increase the steel percentage
crossing the joint to avoid premature opening of the same during
service.
Machinery and labour:
The mixer, vibrator concrete pump as per requirement should be
readily available. For critical machinery, spares should also
be made ready. Adequate labour for concreting should be mobilised.
Special provisions:
The movement of labour will depend on the sequence of concreting.
Once this is finalised, arrangements for wooden planks to serve
as bridge for the labour movement without affecting the rebar
grill must be got ready. Labour should never be allowed to walk
on the reinforcement directly.
Deployment of checking
personnel: During concreting one supervisor should
be positioned at the mixer end to check the proper batching of
ingredients. One person is required to see that the reinforcements
are not displaced during concreting and proper compaction is being
effected at the location of concreting. Preferably a carpenter
is required to check the formwork, scaffolding system and the
props to ensure that they are not disturbed due to wet weight
of concrete.
Location of steel
grill: Cover blocks and chairs should be checked
to ensure tolerances for the steel grill. Top steel should not
get dislodged due to either weight of concrete, construction operations
or labour.
Methods to avoid cracks:
The concrete should not be finished smooth or done up with a trowel
as it will encourage the laitance to come to the surface, thereby
forming a weak top layer. No dry cement should be sprinkled to
absorb moisture. These will encourage micro-shrinkage cracks.
All cold joints should be avoided. It is also necessary to moisten
the formwork before starting the concreting work.
Test cubes:
It is always advisable to prepare test cubes of required number
depending on the volume of concrete executed. The tests on these
will also decide when the shuttering can be released. This will
act as a check on the final resulting strength of the concrete.
Special weather precautions:
During concreting in summer season, it is advisable to cover the
freshly laid wet concrete by moist gunny bag. Drastic drying of
green concrete should be prevented in the interest of avoiding
plastic shrinkage cracks. In case of rain or heavy winds concrete
should be protected with a tarpaulin.
Post-construction
measures: De-shuttering of vertical sides of the
slab can be done after 24 hours. For curing, 2mx2m ponds made
with lean mortar on the surface of concrete may be used.
Curing of the slab should start before the top surface starts
drying and should be continued for 10 to 20 days depending on
the type of cement used. De-shuttering of slabs can be done after
7, 10 or 15 days depending on the type of cement and the span
of the slab.
Hacking the bottom of the slab for making it rough is not permitted
as this act causes micro cracking.
Instead, a good bonding agent will have to be applied before
plastering to ensure good bond between the plaster and concrete.
However, it is best to leave the concrete as `form finished'.
If meticulous care is taken during formwork preparation, then
there will be no need for plastering for hiding the defects in
concrete!